|
||||||
Why Do Construction Claims Occur?Solving the Problems is Best, but That’s not Always Possible
Construction involves risks and unknowns. These often gives rise to construction claims. The engineer's role is to solve the problem before it becomes a claim.
Consulting engineers who work on projects that include construction often find themselves having to deal with claims from contractors, and less often from the facility owner. Construction claims occur:
Construction Contract Provisions for Changed ConditionsNo matter how well the construction drawings and specifications are prepared, every detailed item of a construction project cannot be known or shown. Some things can be learned only as construction is taking place. Most construction contracts include the recognition that changes will be either necessary or desirable. For example the Engineers Joint Contract Documents Committee [EJCDC] General Conditions include several paragraphs which anticipate the types of changes that are likely to occur.
However, changes can arise that are not related to discrepancies in the construction documents. When the contractor begins digging, underground conditions may differ from what everyone assumed. Because of this, the EJCDC General Conditions specifically state what to do when differing subsurface conditions are encountered.
The General Conditions Include a Formal Process for Dealing With Contract ChangesFor this reason, most construction contracts have provisions for making changes to the work, including changes in contract price and contract times. The EJCDC General Conditions provide three ways to change the contract documents.
The EJCDC general conditions also have a provision for how to deal with the cost of the work performed under a change. This can be a useful provision when the parties simply cannot come to agreement on changes in price. Work Hard to Come to Agreement so that a Change Does not Become a ClaimWhen either the contractor or the owner requests a change in the contract documents, which will likely include a change in contract price and contract times, the most import part of the engineer’s job is to get the two parties to agree to an equitable change. If the two cannot agree to a change, the next step is for either party to file a claim for what they believe they are entitled to. A claim will typically be more difficult to resolve than a request for a change. The fact that a claim is submitted indicates the process of working together has already begun to break down. The engineer’s best option is to bring the two parties agreement on the change needed. Often the owner will abide by the engineer’s judgment, providing the change is not too large. However, if the changed condition results in a decrease in contract price or contract times, the contractor is likely to balk, and it may be the owner who will be led to file a claim. More information on resolving claims is given in the article "Construction Claims - Use the General Conditions." The engineer will do well to help the owner and contractor to agree to changes and not let changes become claims. Claims are much more difficult to work through, have the possibility of becoming disputes, and put a greater burden on the engineer. Source: Engineers Joint Contract Documents Committee, Standard General Conditions of the Construction Contract, 2002
The copyright of the article Why Do Construction Claims Occur? in Civil Engineering is owned by David Todd. Permission to republish Why Do Construction Claims Occur? in print or online must be granted by the author in writing.
|
||||||
|
|
||||||
|
|
||||||